TIMELINE FOR COMPLETION OF JAIL BUILDING REPAIRS
posted on: Monday, November 19, 2007
As a Quorum Court member and this years budget committee chairman, I am working hard to increase the number of jail beds at the Pulaski County Detention Center open to hold prisoners. However, before we can increase our population, we must complete some major repairs to the oldest portion of the jail buildings. The roof over pods A, B, C and D (each of which have the capacity of 80 prisoners) must have major reconstructive repairs done to the roof and interior. The old sections of the jail also need new heating boilers and air conditioning units installed.
Below you will find a link to a timeline, which will show the steps we must complete in order to bring the building back up to occupancy status.
Step 1: An engineering firm has been hired to inspect the current building structure to make sure that it will be safe to repair and put a new roof on the existing structure. This firm has told us that the estimated time needed will be 6 weeks and has started on their evaluation on November 1st. However due to the holidays we do not expect a report back before the first of the year.
Step 2: Once we have a favorable report from the engineers, RFPs will be sent out and an advertisement for bids will be published. This process is expected to take from 30 to 45 days to complete.
Step 3: The bids for the work will be received and submitted for committee approval. This process is expected to take approximately 2 weeks.
Step 4: The winning bid will have to be submitted to the full Quorum Court for final approval and the funds for the repairs appropriated to the project, which will take another 2 weeks.
Step 5: The winning contractor will have to schedule the work to begin which is expected to take another 30 to 45 days.
Step 6: From this point, once the work has begun, the entire project is expected to take approximately 5 months to complete before prisoners can physically occupy these four pods.
By the time the building is ready for occupancy, the funds to operate the additional beds should be available. But the Quorum Court simply MUST hold their current course of responsible appropriation of funds and spending of tax payers dollars. This year, in 2007, the Quorum Court held the line and made hard choices and my goal is to continue that same calling through the upcoming year of 2008.
Allen Kerr
CLICK HERE to see the timeline.
Below you will find a link to a timeline, which will show the steps we must complete in order to bring the building back up to occupancy status.
Step 1: An engineering firm has been hired to inspect the current building structure to make sure that it will be safe to repair and put a new roof on the existing structure. This firm has told us that the estimated time needed will be 6 weeks and has started on their evaluation on November 1st. However due to the holidays we do not expect a report back before the first of the year.
Step 2: Once we have a favorable report from the engineers, RFPs will be sent out and an advertisement for bids will be published. This process is expected to take from 30 to 45 days to complete.
Step 3: The bids for the work will be received and submitted for committee approval. This process is expected to take approximately 2 weeks.
Step 4: The winning bid will have to be submitted to the full Quorum Court for final approval and the funds for the repairs appropriated to the project, which will take another 2 weeks.
Step 5: The winning contractor will have to schedule the work to begin which is expected to take another 30 to 45 days.
Step 6: From this point, once the work has begun, the entire project is expected to take approximately 5 months to complete before prisoners can physically occupy these four pods.
By the time the building is ready for occupancy, the funds to operate the additional beds should be available. But the Quorum Court simply MUST hold their current course of responsible appropriation of funds and spending of tax payers dollars. This year, in 2007, the Quorum Court held the line and made hard choices and my goal is to continue that same calling through the upcoming year of 2008.
Allen Kerr
CLICK HERE to see the timeline.


